Craftsman Remodel - Central Vacuum


Click any picture to supersize it. Sorted by date. To see the latest pictures start at the last page and work your way backwards.

DSCN0015.JPG
Sun, May 22, 2005
DSCN0016.JPG
Sun, May 22, 2005
DSCN0017.JPG
Sun, May 22, 2005
The range centerline is right under a joist. The joist will have to be moved to accommodate a 10" vent. Electrical and plumbing for the range. The range vent will have to pass through where the large drain and central vacuum pipes are currently located.
DSCN0018.JPG
Sun, May 22, 2005
DSCN0027.JPG
Sun, May 22, 2005
DSCN0037.JPG
Fri, May 27, 2005
The kitchen is on the other side of this wall. The central vacuum line will extend out under the cabinet to a toe-kick vacuum opening. Sweep to the end of the cabinet and press a button.
DSCN0038.JPG
Fri, May 27, 2005
DSCN0039.JPG
Fri, May 27, 2005
DSCN0044.JPG
Fri, May 27, 2005
The range will go here. The Sub Zero refrigerator will go here. The electrical still has to be put in for it. Another view of the black gas line going up between the studs.
DSCN0047.JPG
Fri, May 27, 2005
DSCN0053.JPG
Fri, May 27, 2005
DSCN0054.JPG
Fri, May 27, 2005
The ceiling in the library/guest bedroom is staying at 8 feet to allow space for everything to pass through. It's very crowded in the ceiling here. Looking down the hallway towards the kid's bedroom.
DSCN0055.JPG
Fri, May 27, 2005
DSCN0064.JPG
Fri, May 27, 2005
DSCN0066.JPG
Fri, May 27, 2005
The cable bundle will go through the wall to the living room stereo. The soffit was built to hold the vent ducting. Central vacuum at the top of the stairs.
DSCN0070.JPG
Fri, May 27, 2005
DSCN0073.JPG
Fri, May 27, 2005
DSCN0074.JPG
Fri, May 27, 2005
The upstairs heating unit is in a crawl space above the arch. The white pipe is the central vacuum line.
DSCN0076.JPG
Fri, May 27, 2005
DSCN0077.JPG
Fri, May 27, 2005
DSCN0010.JPG
Sat, Jun 4, 2005
In the closet looking towards the master bath. The white pipe on the left is the central vacuum. I like those angled lights in the vaulted ceiling. A joist in the kitchen was moved over to make room for a 10" duct for the range vent. The white central vacuum pipe was cut. Notice the two lights that will hang down over the counter on the right.
DSCN0003.JPG
Mon, Jun 20, 2005
DSCN0005.JPG
Mon, Jun 20, 2005
IMG_0252.JPG
Thu, Aug 25, 2005
The bundle of wires is for TV, phone, and internet to the house. In the corner are central vacuum and tankless water heater hookups. The pipe in the top of the wall is the central vac line into the house. The garage is freshly painted. You can see that the garage door is installed and just needs to be plugged in.
IMG_1550.JPG
Tue, Nov 15, 2005
IMG_1645.JPG
Sat, Dec 10, 2005
The white rectangle is a toe-kick vacuum. The 5" wide Brazilian Cherry floor starts to go in. The central vacuum can be seen to the right.



Last updated: 3/2/06