In this blog I will do my best to describe the process I went through in turning my 1957 Ranch-style house into a 2006 Craftsman house as inspired by the Gamble House in Pasadena. Please feel free to comment on anything I write and ask questions as it is the only way we learn.

Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.


TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???



Biometric Fingerprint Garage Door Opener

Biometric Fingerprint Garage Door Opener
I still don't have any way to get into my garage and have been wondering about a fingerprint scanner mechanism so the kids won't have to remember a code. Well, I just found one that's made by Craftsman. According to info I have read, it can store up to four unique fingerprints and takes about a minute to program it. You can read more about it here.

What I like about it is that you can program a contractor's fingerprint into it for the one or two days he needs access without giving a numeric code. When he's done working, remove the fingerprint from the system and he's locked out!


Add/Review Comments


Sanded and Stained Front Door and Garage

With the sun beating down on the garage door, the mahogany was getting bleached. I decided to have the garage door and front door sanded and stained. The garage door took three weeks to do. What a job!

Craftsman front door is sanded and ready for stain. Craftsman garage door is sanded and ready for stain.
Staining the mahogany Craftsman garage door The stained mahogany Craftsman garage door

Add/Review Comments


Garage Door Installed, Interior Primed, Bathroom Floated, Ceiling Beams Installed

Not much has happened the last month. Vacations and other jobs have gotten in the way. However, the work that has been done is looking really good. So here's the run down.
• All interior doors have been ordered but we have to wait about a month. Expected delivery is 9/14/05.
• The garage door was installed.



• Interior of house and garage has had two coats of primer applied.
• Master bathroom has been floated and is ready for tile.
• The ceiling beams are being installed single-handedly by Dave Barlow. The planning for this was extremely difficult as there is quite a bit of wood and detail in a Craftsman style house. We are designing the layouts on the fly for the ceiling, crown moulding, plate/picture rail, floor trim, wainscoting, and staircase. All of these pieces tie together as one entire wood 'system'. Our design of this is staying about one or two steps ahead of the build. One problem is that we don't have our wood floors in yet so we can't build the jambs up from the floor.

Dave Barlow installs the living room beams

Add/Review Comments


Low Voltage Wiring, Electrical, Plumbing, Garage Door Ordered, Issues in the Kitchen

• Still working on updating the pictures. They should be coming within the week.
• There is still quite a bit to do before inspection. We had a telecom installer come out and install phone (Cat 5), cable TV (RG6), and Ethernet (Cat 6). There was about 1700 feet of ethernet wiring installed. It's easier to put it in now than later. For example, it's behind TVs, in the kitchen, etc. I won't be using it but in 10 years or so it may be needed for home automation purposes. It's also a good selling point if I ever go down that path.
• Wall sconces have been wired.
• Plumbing is almost complete. Just finishing up the gas lines.
• The garage door has been ordered from Designer Doors. This is going to be really nice!
• Issues continue to test my patience in the kitchen. There are so many wires, pipes, and ducts running through the ceiling that we are having trouble figuring out how to get a 10" duct from the range hood over about 10" off center to fit between two joists and vent out the wall.
• The ceiling beam patterns are a challenge since we decided to add the kitchen into the remodeling mix. We decided to stop the ceiling beams at the boundary between the kitchen and dining room so the living and dining rooms only have beams. Kitchen ceiling is TBD.
• The remaining part of the block wall on the rear patio was cut down yesterday.