In this blog I will do my best to describe the process I went through in turning my 1957 Ranch-style house into a 2006 Craftsman house as inspired by the Gamble House in Pasadena. Please feel free to comment on anything I write and ask questions as it is the only way we learn.
TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
The Finishes are Going In
• The master bathroom has been tiled and looks great!

• Cherry cabinets have been installed in the kitchen, master bath, and laundry room. Unfortunately, the kitchen sink cabinet was 3/4" off center from the window. The cabinet had to be shortened by 3/4" on both ends to keep it symmetric and centered on the window.

• I have purchased the soapstone slabs for the kitchen and laundry room from Soapstone West in Escondido, CA.
• Brazilian Cherry floors have been ordered from Dutko Hardwood Floors in Lawndale, CA and will be installed the first week of December. Talk about a backlog.
• The fireplace mantel has been installed and stained. Plaster will go above it and Moonlight flagstone will go below. It will be cut into manicured blocks of varying size.

• Actual work has started on the staircase. There was a lot of planning to get to this point.
• The hot tub has been delivered. We're just waiting for power now.

• The Golden Busckskin flagstone has been installed on the front and back patios.

• The green slate has been installed on the balconies.
• Paint samples are all over the walls. I hear they will start within 2 weeks with the paint.

• Interior doors are installed and stained.

Cabinets, Plumbing, Electrical, Insulation, Surround Sound, Roof Work, Shower Mopped,.....
• All plumbing and electrical in the master bathroom has to shift to the left by about a foot since we had a designer lay out the cabinets.
• All insulation has been put in.
• I installed in-ceiling speaker brackets for surround sound in the living room.

• Copper flashing is going on the roof.

• The shower has been hot-mopped. We were told to pick out all bathroom tile and balcony and laundry room flooring this week.

• Skylights have been framed.

• The Thermador range and Thermador dishwasher were delivered last week. I found a place in Alabama (Fredrickson's Tire and Appliance) with amazing prices through eBay. They were clearing out a supply of Thermador appliances from a warehouse that closed down. They bought everything up and were liquidating at wholesale prices.
• With the extended garage roof you now hit your head when walking around the corner. So, we dug down about 2 feet around the garage to lower the grade.