Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.
TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Gamble House Lights, Floor Issue, Fireplaces, Ebony Plugs, Kitchen Tile
• I created the stained glass for the light in the December 18th blog post only to find out that half of them were too small. After another week of stained glass work, I finished and my fingertips were raw. I brought the glass panels to Old California Lantern Company for installation and received the lights about 2 weeks ago. They are absolutely stunning!
• The floors are installed. Lesson learned - make sure the installers verify that the door still opens before the whole thing is laid!!!
• The kitchen, laundry room, and master bathroom American cherry cabinets have been stained with Jel'd Stain Red Mahogany by Wood Kote.
• The walk-in closet cabinets are almost complete.
• The master bedroom fireplace is covered with a beautiful Batchelder tile from Mission Tile West in Santa Monica.
• The living room entertainment center is built and ready for finishing.
• Dave Barlow is installing the ebony plugs in the scarf joints around the house.
• The living room fireplace is having Moonlight flagstone installed right now. It's a very slow process as each piece is being chiseled to the right dimensions. Look on the left part of the mantel and you can see my sugar cube mockup of the stone corner. I made this to make sure they understood how I wanted the 45-degree angles handled.
• The appliances will be installed tomorrow.
• Clear-coating of the mahogany will start in about 2 weeks followed by painting the walls and ceiling.
• Glass tile from Mission Tile West has been installed in the kitchen. It looks amazing!
Well, I'm going to start uploading the pictures now and then I'm off to Kauai for my 40th birthday.
Soapstone Counter Installation
Below is a play-by-play of the installation.
These guys drove in from Arizona, and within 2 days measured, fabricated, and installed the soapstone countertops.
These slabs are HEAVY at 20 lbs/sq ft.
There is a 3/8" overlap of the sink. The holes for the faucet, soap, drinking water, and vent are drilled.
Black epoxy is mixed up to join the soapstone pieces and fill in any voids.
A ding is repaired with the special epoxy. After it dries you can't even see it.
Even through the talcum powder layer you can see the caramel vein showing through.
Soapstone installation is messy work.
Soapstone is much denser than granite and can't be stained. However, it is soft enough so that hand sanding can be accomplished to smooth the edges.
This looks gray now but wait until it's oiled.
I oiled the soapstone with mineral oil. It's shiny because it's still wet. When dry, it will have a matte finish.
The counter looks great! The door to the laundry room has a "Delta" pattern in it.
The Finishes are Going In
• The master bathroom has been tiled and looks great!
• Cherry cabinets have been installed in the kitchen, master bath, and laundry room. Unfortunately, the kitchen sink cabinet was 3/4" off center from the window. The cabinet had to be shortened by 3/4" on both ends to keep it symmetric and centered on the window.
• I have purchased the soapstone slabs for the kitchen and laundry room from Soapstone West in Escondido, CA.
• Brazilian Cherry floors have been ordered from Dutko Hardwood Floors in Lawndale, CA and will be installed the first week of December. Talk about a backlog.
• The fireplace mantel has been installed and stained. Plaster will go above it and Moonlight flagstone will go below. It will be cut into manicured blocks of varying size.
• Actual work has started on the staircase. There was a lot of planning to get to this point.
• The hot tub has been delivered. We're just waiting for power now.
• The Golden Busckskin flagstone has been installed on the front and back patios.
• The green slate has been installed on the balconies.
• Paint samples are all over the walls. I hear they will start within 2 weeks with the paint.
• Interior doors are installed and stained.
Camera Broken, Drywall Taped and Sanded, Starting Staircase, Siding Complete
• Drywall is sanded and just about ready for primer.
• Dave Barlow is working the staircase and will be doing other fine carpentry in the house. He is creating mockups of everything out of MDF (fiberboard) prior to cutting the real wood.
• All shingle and stone siding is installed.
Low Voltage Wiring, Electrical, Plumbing, Garage Door Ordered, Issues in the Kitchen
• There is still quite a bit to do before inspection. We had a telecom installer come out and install phone (Cat 5), cable TV (RG6), and Ethernet (Cat 6). There was about 1700 feet of ethernet wiring installed. It's easier to put it in now than later. For example, it's behind TVs, in the kitchen, etc. I won't be using it but in 10 years or so it may be needed for home automation purposes. It's also a good selling point if I ever go down that path.
• Wall sconces have been wired.
• Plumbing is almost complete. Just finishing up the gas lines.
• The garage door has been ordered from Designer Doors. This is going to be really nice!
• Issues continue to test my patience in the kitchen. There are so many wires, pipes, and ducts running through the ceiling that we are having trouble figuring out how to get a 10" duct from the range hood over about 10" off center to fit between two joists and vent out the wall.
• The ceiling beam patterns are a challenge since we decided to add the kitchen into the remodeling mix. We decided to stop the ceiling beams at the boundary between the kitchen and dining room so the living and dining rooms only have beams. Kitchen ceiling is TBD.
• The remaining part of the block wall on the rear patio was cut down yesterday.