Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.
TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Job Shut Down Due to Rain
Mon, Feb 28 2005 09:26 PM
| Construction, Remodel
| Permalink
Well we got about 10 inches out of that storm. The job was shut down for over a week. This makes for about 6 weeks of delay due to rain so far. A lot of water came in on the remaining wood floor. Let's see what's left of it when the masonite is removed. The tarps couldn't handle all of the water and the ceiling fell down in one of the downstairs bedrooms. Second floor framing work starts today.