Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.
TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Everyone is Working, Picking Fixtures, Designing Landscape, Where's My Garage
Tue, Apr 12 2005 02:19 PM
| Bathroom, Bungalow, Construction, Craftsman, Landscaping, Remodel, Steam shower
| Permalink
• The rough plumbing is going well. Only about 4 more days until it's done.
• The master bathroom shower, sink, and tub fixtures were picked today. They are made by Phylrich - Carrara Beige Model Series. The finish is oil rubbed bronze with the beige marble handles.
• Chose Mr. Steam MS-400T for the master bath steam shower. I purchased it and then found it for about $150 less. Oh well, maybe I'll save next time. This site has everything!
• The master bathroom shower, sink, and tub fixtures were picked today. They are made by Phylrich - Carrara Beige Model Series. The finish is oil rubbed bronze with the beige marble handles.
• Chose Mr. Steam MS-400T for the master bath steam shower. I purchased it and then found it for about $150 less. Oh well, maybe I'll save next time. This site has everything!
• The electrician started today and mounted electrical boxes around the house. It seems the code of a box every 6 feet is excessive.
• The garage was torn down today due to wood rot and termites in preparation for the new garage framing and roof. This was not part of the original plan.
• Hired John Bauman, landscape designer and former owner of the Begonia Farm Nursery.