TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Windows and Doors Ordered
Tue, Jan 18 2005 05:00 PM
| Construction, Door, Foundation, Remodel, windows
| Permalink
Loewen windows and doors were ordered today. They will be push-out, french casements in a cranberry color.
On a completely unrelated note, I was told that the concrete for the foundation under the house will be poured on Friday, 1/21/05.
On a completely unrelated note, I was told that the concrete for the foundation under the house will be poured on Friday, 1/21/05.