In this blog I will do my best to describe the process I went through in turning my 1957 Ranch-style house into a 2006 Craftsman house as inspired by the Gamble House in Pasadena. Please feel free to comment on anything I write and ask questions as it is the only way we learn.

Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.


TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???



Retainer Given to Architect

Today is a big day! A retainer was given to Olympia Greer, our architect, to start work.
Add/Review Comments


Architect Selection

After interviewing several people, we chose to go with Olympia Greer. We chose her because she has a great design sense and lives and works in Palos Verdes Estates.
Add/Review Comments


The Permit & Construction Process

Construction Process
Before I get into the daily details, it would first be beneficial to tell you how the construction process works in Palos Verdes Estates. I found a great picture on their web site that is posted below. Basically, all construction needs to go through the Art Jury, part of the PVE Homes Association, and the the City's Planning Commission.

The first step is to get your drawings approved for aesthetics by the Art Jury. After their blessing, you can then go to the Planning Commission where they will weigh in on neighborhood compatibility, and listen to any neighbor's concerns. If there are concerns, you go before the Planning Commission and defend or compsomise on your position. The 5 members then vote to approve or deny your request for a permit. A majority of 3 members is required to grant approval.
Add/Review Comments


Next Page

Be sure to browse the 2,000 picture Photo Gallery for more step-by-step construction details.