Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.
TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Time to Redesign the Bathroom
Fri, Mar 4 2005 09:29 PM
| Construction, Framing, Remodel, windows
| Permalink
Today's GOTCHA. I was at the house looking around at the framing on the second floor and noticed that the master bath window seemed much larger than what I had remembered so I pulled the drawings and measured it. It says the window should be 4 feet wide with a 4 foot wide shower. Then I looked at the window schedule and saw that 2, 2'-6" windows were to be ordered for the spot. Now my shower would be quite narrow. I decided to swap the shower with the counter at the opposite corner of the room. This will not only give me a larger shower but will move all of that plumbing to the outer wall of the house between the tub and toilet. A win-win in my opinion.
Add/Review Comments
The Steel Beam is Installed
Fri, Jan 14 2005 04:29 PM
| Balcony, Construction, Framing, Remodel
| Permalink

This beam was put in to support the second floor balcony.