Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.
TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Another Painting Lesson Learned, Stair Railing Being Refinished, Electrical Done, Pond Built
• Skim-coated all walls in house in preparation for paint. Individual patching of blemishes was not working and we needed to overhaul all walls.
LESSON LEARNED: An eggshell finish is great for a house with kids but it's also great at pointing out every imperfection in the wall. If you don't have kids then definitely use a flat paint. We are using a flat paint for the ceilings.
• Painting is all that is left with the walls. Stefan is continuing and 3 more painters come in next week to finish the place out.
• The stair railing has been fit and will be sent out for refinishing.
• All data, phone, and cable has been hooked up and patch panels installed in garage.
• All exterior wall sconces installed.
• Office is 100% complete.
• Backyard is fully powered.
• Pond is fully operational with fish, snails, and tadpoles.
• Spa is being filled.
• Trees have been ordered.
• Front pathway is complete.
Gamble House Lights, Floor Issue, Fireplaces, Ebony Plugs, Kitchen Tile
• I created the stained glass for the light in the December 18th blog post only to find out that half of them were too small. After another week of stained glass work, I finished and my fingertips were raw. I brought the glass panels to Old California Lantern Company for installation and received the lights about 2 weeks ago. They are absolutely stunning!
• The floors are installed. Lesson learned - make sure the installers verify that the door still opens before the whole thing is laid!!!
• The kitchen, laundry room, and master bathroom American cherry cabinets have been stained with Jel'd Stain Red Mahogany by Wood Kote.
• The walk-in closet cabinets are almost complete.
• The master bedroom fireplace is covered with a beautiful Batchelder tile from Mission Tile West in Santa Monica.
• The living room entertainment center is built and ready for finishing.
• Dave Barlow is installing the ebony plugs in the scarf joints around the house.
• The living room fireplace is having Moonlight flagstone installed right now. It's a very slow process as each piece is being chiseled to the right dimensions. Look on the left part of the mantel and you can see my sugar cube mockup of the stone corner. I made this to make sure they understood how I wanted the 45-degree angles handled.
• The appliances will be installed tomorrow.
• Clear-coating of the mahogany will start in about 2 weeks followed by painting the walls and ceiling.
• Glass tile from Mission Tile West has been installed in the kitchen. It looks amazing!
Well, I'm going to start uploading the pictures now and then I'm off to Kauai for my 40th birthday.
Wall Sconce Stained Glass, Wood Floors Being Installed
• I'm really busy now creating the stained glass for some authentic Gamble House reproductions. The stained glass will be different and my own design. I'll tie that into the front door window whenever I get around to it. Go to Old California Lantern Company to see the best Arts & Crafts lanterns. I went in there and 3 1/2 hours later I outfitted my entire house.
• The hardwood floors are being installed right now. It is long-length (8'-16'), quarter-sawn, 5"-wide, Brazilian Cherry. We are having a slight bevel put between the planks to give it an older look. The floor will be stained black, sanded, and then stained with a green dye to subdue the bright reds associated with Brazilian cherry.
Next Page