TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Retaining Wall and Fireplace Mantel Complete, Upstairs Painting, Historic Lighting
• The master bedroom fireplace mantle is complete.
• The painters are starting upstairs tomorrow. They have a lot of sanding to do.
• Su Bacon of Historic Lighting is coming out tomorrow to see the house and advise on entry and stairway chandeliers I'm purchasing from her. They are designed by the craftsman Karl Berry from New York. Su has been a consultant on many big projects. When we went into her Arcadia store, we found out that she was consulted for lighting on the TV show Extreme Makeover: Home Edition. I told her about the living room fireplace we were creating based on a picture I saw in a magazine. She knew it well as she was the designer. How cool is that!
• My updated guess on a move-in date is mid May.
The Finishes are Going In
• The master bathroom has been tiled and looks great!
• Cherry cabinets have been installed in the kitchen, master bath, and laundry room. Unfortunately, the kitchen sink cabinet was 3/4" off center from the window. The cabinet had to be shortened by 3/4" on both ends to keep it symmetric and centered on the window.
• I have purchased the soapstone slabs for the kitchen and laundry room from Soapstone West in Escondido, CA.
• Brazilian Cherry floors have been ordered from Dutko Hardwood Floors in Lawndale, CA and will be installed the first week of December. Talk about a backlog.
• The fireplace mantel has been installed and stained. Plaster will go above it and Moonlight flagstone will go below. It will be cut into manicured blocks of varying size.
• Actual work has started on the staircase. There was a lot of planning to get to this point.
• The hot tub has been delivered. We're just waiting for power now.
• The Golden Busckskin flagstone has been installed on the front and back patios.
• The green slate has been installed on the balconies.
• Paint samples are all over the walls. I hear they will start within 2 weeks with the paint.
• Interior doors are installed and stained.
Next Page
Be sure to browse the 2,000 picture Photo Gallery for more step-by-step construction details.