Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.
TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Roof Papered, Skylights In, Siding Ordered, Ceiling Layouts, Rough-Ins Continue
• Velux skylights will be added to the entry, and all downstairs bedrooms. These skylights have remotely controlled blackout blinds built in. I definitely wanted a chandelier in the entry but Amy was saying it was too dark. Our solution is to put in a 24"x24" skylight that is parallel to the floor instead of the vaulted ceiling. Wood trim will be placed around the opening to match window and door trims. From the four corners, wires will be strung to hold an as yet to be determined chandelier. I'll probably have to make it. I'm envisioning a 4-sided inverted pyramid with stained glass panels. During the day it will be illuminated by the skylight above and at night it will work as a regular chandelier, i.e., it will always be lit up.
• The cedar, shingle siding has been ordered from Cedar Valley in Hollister, California.
• Beam locations in the living room, dining room, and kitchen have been identified by string. This allowed rough-ins of plumbing, electrical, HVAC, and central vacuum systems. Inspection should be next week.
Next Page
Be sure to browse the 2,000 picture Photo Gallery for more step-by-step construction details.