In this blog I will do my best to describe the process I went through in turning my 1957 Ranch-style house into a 2006 Craftsman house as inspired by the Gamble House in Pasadena. Please feel free to comment on anything I write and ask questions as it is the only way we learn.

Note: Since completion of the house I have also decided to allow guest bloggers to post articles related to remodeling. This continues the education process.


TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???



Stairwell Wainscot, Concrete Poured, Work Stopped, Gone Surfing

I received a letter from the City stating that the permit will expire on May 12. At least we now have a target date. I would still like to shoot for final inspection by May 1st.
• We are laying out the stairwell wainscoting. It will be Honduran Mahogany with 6 distinct layers to give it a depth effect. Just wait and see...
• Drainage was put in on the North side of the house.
• Concrete was poured on the North side so we can now build the block wall for the planter.
• Two carpenters and the electrician are surfing and camping at Big Sur for the last two days. My GC is sick with food poisoning and Dave, the finish carpenter is on another job for 2 days. In other words, NO WORK FOR THE LAST 2 DAYS IN THE HOUSE. How in the world will we finish in time when things like this happen?
Add/Review Comments


Next Page

Be sure to browse the 2,000 picture Photo Gallery for more step-by-step construction details.