TIMELINE
Architect Selection - December 2002 through January 2003
Getting a Permit - January 2003 through November 2004
Construction - November 2004 through September 2006
Post Construction - October 2006 through ???
Patio Poured, Ordered Door, Interior Design Starting
• All doors are now installed except for the front door (being built) and the side door (just ordered it). The side door is made by TM Cobb. It is a Stickley model with a mantel from the Greene door.
Edited October 29, 2005: The actual door interior and exterior.
• Hose bib locations have been identified.
INTERIOR DESIGN STARTING
I had no idea that I was going to be designing the interior of this house on the fly.
• Spent the last few days identifying all lighting that was not on the original plans. This includes wall sconces inside and outside.
• Roughly laid out the beam design separating the living room and dining room.
Windows In, Roof Sheeted, Ordered Fixtures, Lessons Learned
• For the past week, I was pushing the masons to hurry up and put in a block wall around part of the patio according to the plans. Amy came over to see it that night and we both decided it was too tall and closed in the patio too much. The following day I had the guys tear it out. It wasn't very fun telling them that.
• Installed all windows. Working on doors now.
• Ordered the master bath plumbing fixtures in oil-rubbed bronze (Phylrich Carrara Beige Marble) and the steam shower system (Mr. Steam)
• The roof is sheeted, now it's ready for waterproofing.
LESSONS LEARNED
• Heating ducts have been a pain in the neck. Multiple small changes have been needed to make the design work. A lesson learned is that none of the subcontractors know how the other is planning on roughing out their lines. As a result, heating ducts start to go in and one by one I tell them why it can't go in a certain spot. A soffit was created upstairs to handle the ducting. Downstairs, ducting is being run without knowledge of the final beam layouts on the finished ceiling. I'm having stuff moved. They wanted to run ducts right where I need my range vented out in the kitchen, etc., etc.
The bottom line is make sure you are on site a lot during the rough-ins to make sure everything works. Only you will know how the end product is going to be used.
First Window Installed
Windows and Doors Delivered
Everyone is Working, Picking Fixtures, Designing Landscape, Where's My Garage
• The master bathroom shower, sink, and tub fixtures were picked today. They are made by Phylrich - Carrara Beige Model Series. The finish is oil rubbed bronze with the beige marble handles.
• Chose Mr. Steam MS-400T for the master bath steam shower. I purchased it and then found it for about $150 less. Oh well, maybe I'll save next time. This site has everything!
• The electrician started today and mounted electrical boxes around the house. It seems the code of a box every 6 feet is excessive.
• The garage was torn down today due to wood rot and termites in preparation for the new garage framing and roof. This was not part of the original plan.
• Hired John Bauman, landscape designer and former owner of the Begonia Farm Nursery.
Fireplace Construction Starts
Eaves and Rafters Stained Today

Paint Colors Selected and Front Door Started
• Gave Joe Madden of Madden Millworks in San Pedro the go-ahead to start construction of the front door.
Front Door Design
Rough Idea

By the way, the rain is coming again next week. We should get another 2 inches which will push L.A. up to the second rainiest ever. I guess I was just lucky to start building this year during this monsoon season. Maybe we can be number one soon. UGH!
------------------------------------------------------------------------
Modified on 1/23/08
Here is a picture of the actual door at the mill and with the final stained glass. If you look closely at the raw door, you can see the three plugs at the base of the window frame. These remove to allow me to remove the frame and swap out the glass at anytime.


Time to Redesign the Bathroom
Next Page