Craftsman Remodel - Framing page 4


Click any picture to supersize it. Sorted by date. To see the latest pictures start at the last page and work your way backwards.

DSCN0045.JPG
Wed, Mar 9, 2005
DSCN0046.JPG
Wed, Mar 9, 2005
DSCN0047.JPG
Wed, Mar 9, 2005
Looking down at the vertical post that needs to be shortened. A bit closer to the tree than I was expecting. Here comes the rain.....again!
DSCN0048.JPG
Wed, Mar 9, 2005
DSCN0049.JPG
Wed, Mar 9, 2005
DSCN0050.JPG
Wed, Mar 9, 2005
The previously crooked beam was straightened and the braces are put in place. Master bedroom balcony.
DSCN0051.JPG
Wed, Mar 9, 2005
DSCN0052.JPG
Wed, Mar 9, 2005
DSCN0053.JPG
Wed, Mar 9, 2005
Looking from the new office towards the master bedroom balcony. A lot of pieces are coming together at this corner. The Hardy Frames below are needed to structurally support all of this weight. The outline of the patio.
DSCN0054.JPG
Wed, Mar 9, 2005
DSCN0055.JPG
Wed, Mar 9, 2005
DSCN0056.JPG
Wed, Mar 9, 2005
The outline of the spa in the backyard. You can also see the cantilevered balcony. The rafter tails are getting ready to be rounded off with a router. The rain never stops!
DSCN0057.JPG
Wed, Mar 9, 2005
DSCN0058.JPG
Wed, Mar 9, 2005
DSCN0061.JPG
Fri, Mar 11, 2005
The second floor is taking shape. Let's get that roof on before the next rain. The north side of the house is still a mess. Rafter tails as cut by the lumber yard.
DSCN0063.JPG
Fri, Mar 11, 2005
DSCN0065.JPG
Fri, Mar 11, 2005
DSCN0067.JPG
Sat, Mar 12, 2005
Rafter tails after being routered. Bill and Bruce finish up the balcony joists. Hello neighbors. The view from my neighbor's driveway. I'm taking the hedge out.
DSCN0068.JPG
Sat, Mar 12, 2005
DSCN0072.JPG
Sat, Mar 12, 2005
DSCN0073.JPG
Sat, Mar 12, 2005
The rafter tails are going in place. The master bedroom and office balconies are joisted and sheeted. See how the rafter is sandwiched into the structure.
DSCN0074.JPG
Sat, Mar 12, 2005
DSCN0075.JPG
Tue, Mar 15, 2005
DSCN0001.JPG
Wed, Mar 16, 2005
DSCN0002.JPG
Wed, Mar 16, 2005
DSCN0001.JPG
Tue, Mar 29, 2005
DSCN0002.JPG
Tue, Mar 29, 2005
The rafters are notched and overlay the ridge beam where they overlap at the top. A very strong structure. Bruce starts to put the tongue & groove (T&G) on the front of the second story roof. Rafter tails in the corner. One is used to support the other barge rafter.
DSCN0003.JPG
Tue, Mar 29, 2005
DSCN0004.JPG
Tue, Mar 29, 2005
DSCN0005.JPG
Tue, Mar 29, 2005
The windows should arrive in about a week so the window and door openings are being framed out. Looking at the front, second story rafter tails. The highest ridge beam in the house is on the left. The right side of the roof was stopped short to allow for a shed dormer to be put in.



Last updated: 11/13/05